Alcooad Bioenergia

Corn ethanol distillery, Tangará da Serra/MT

About

  • Construction and assembly of process piping, process equipment, and utilities;
  • Materials: Stainless steel 304, Sch. 5S, 10S, and OD, plus carbon steel Sch. 40, 80, and P11;
  • Pipe diameters - from 1/2” to 40”
  • 11,700 linear meters of pipe;
  • 3,450 linear meters of welding;
  • Workforce: 85 employees;
  • Execution period: from March 2020 to December 2021;
  • Execution hours: 87,100h.